Homeowner guide

How to compare landscape bids.

Three bids for the same yard usually describe three different jobs. This is how I read a bid, in the order I read it.

G-1

Why three bids rarely compare

One bid includes demolition and haul-off. One assumes the gas line is somebody else's problem. One prices a patio 200 square feet smaller than the one you asked for. The lowest number is often the one that left the most out.

I spent thirty years on the build side of this trade, writing these bids. Now I work for homeowners. When I review your bids, I'm not one of the bidders, so nobody bidding your project pays me.

G-2

Step 1: Make every contractor bid the same job

A bid can only be compared if it prices the same work. Before you ask anyone for a number, put the job in writing:

Give every bidder the same package and ask them to price it as drawn. If one of them suggests a change, ask for it as a separate line so the base numbers still line up.

If you already have bids and no plan, list what each one includes side by side. The gaps show up fast.

G-3

Step 2: Check who is behind each bid

Every California contractor's record is public and costs nothing to check at cslb.ca.gov. Look up the license number on each bid and confirm:

Then ask each bidder for a certificate of general liability insurance, sent to you by their insurance agent and not by the contractor.

Check the salesperson too. Anyone who sells you a home improvement contract and is not an owner or officer of the company must be registered with the state, and their name and registration number belong on the contract.

G-4

Step 3: Read what is left out

Exclusions and allowances are where a low bid hides. Read them before you read the price.

Often left outWhat to ask
Demolition and haul-offAre removal, hauling and dump fees in the price?
Soil export or importHow many yards of soil leave or arrive, and who pays if it is more?
DrainageWhere does the water go, and is that work priced?
Gas, electrical and water runsWho trenches and runs each line, from where, and how far?
Permits, engineering and HOA submittalsWho prepares them, who pays the fees, and who waits on the approval?
Access and site conditionsWhat happens to the price if you hit rock, or equipment can't fit through the side yard?
Repairs afterwardWho fixes irrigation, fencing and stucco damaged during the work?

Allowances are placeholders for things not yet chosen, such as tile, appliances or plants. An allowance is a guess, and a low guess makes a low bid. Ask each bidder what the allowance buys, by product name, and compare it with what you intend to buy.

G-5

Step 4: Read the payment schedule

California law sets the limits on what a contractor can collect and when. A bid that ignores them tells you something about the bidder.

Be wary of a schedule that asks for money for “mobilization,” a “materials deposit,” or “plans and permits” before any work starts. The Contractors State License Board publishes these rules for homeowners at cslb.ca.gov.

G-6

Step 5: Ask how the job will run

Three questions separate a contractor who has planned your job from one who has only priced it.

G-7

What a low bid usually means

A bid well below the others is not automatically a bargain or a trap. It usually means one of four things:

  1. Something was left out (Step 3).
  2. The allowances are low.
  3. The contractor wants the work and has cut the margin. That can be a fair deal if the license, insurance and references hold up.
  4. The contractor plans to make it back on change orders.

You can find the first two by reading. You find the last two by asking the Step 5 questions and calling two recent customers. The right bid prices the whole job and comes from a contractor who can show you one like it that they built.

G-8

The checklist

Print one copy for each bid.

G-9

Questions people ask me

How many bids should I get?

Three is enough if all three price the same plan. Five bids on five different scopes tell you less than two bids on the same one.

Should I take the lowest bid?

Take it when it prices the same scope as the others and the contractor checks out. Otherwise the lowest bid is usually the most incomplete one.

My bids are $40,000 apart. Is someone overcharging?

More often they are pricing different jobs. Put them on the same scope first. If a real gap remains, it is worth a conversation with both bidders.

Do I need a design before I get bids?

For anything beyond a simple patio, yes. Without a plan, each contractor designs the job in their head and prices their own version.

Can you look at bids I already have?

Yes. That is my bid review, a flat $950. I put the bids on the same scope, verify the license, bond, workers' comp and liability on each, and read the payment schedule, allowances and exclusions before you sign.

G-10

Want a second set of eyes?

I review landscape and pool bids for homeowners in South Riverside County and North County San Diego, for a flat $950. When I review your bids, I'm not one of the bidders, and no contractor on your project pays me.

Call (951) 428-8843 Text me